- Call To Order for MSD Board Meeting
- Board Meeting Minutes Approval
- Approval of March 22, 2004 MSD Board Meeting Minutes
- Chair and Executive Director Reports
- Calendar of Events
- Emergency Response Summaries Report for January-February, 2004
- Emergency Procurement Report 110 N. Spring Street Blockage
Removal, Emergency Contract 02-2004/Basham Construction & Rental Co.,
Inc
- Personnel Committee Report
- Exceptionally Achieves Performance Evaluations
|
Angela Akridge
|
Saeed Assef
|
Rebecca Bennett |
Vince Bowlin
|
|
Julie Buckler
|
Dave Carty
|
Bill Chamberlain
|
Kathy Cooksie
|
|
Kim Decker
|
Marion Gee
|
Michael Griffith
|
Carol Guntle
|
|
Tom Harlow
|
Craig Jones
|
Eric Kalbhin
|
John Loechle
|
|
Kathy Lynch
|
Garry Morrison |
Jim Porter |
Carl Randol
|
|
McKinley Reed
|
Sandra Schmitt
|
Sally Smither
|
Kristy Southard |
|
Gail Vogel
|
Tim Wallen
|
Pat Weathers |
|
- New Business
OPERATIONS TEAML
- Procurement of Liquid Oxygen (LOX), Annual Contract/BOC Gases,
Inc.
- MFWTP Polymer Products Procurement/Polydyne, Inc.
GENERAL
- Oracle Software Maintenance/Oracle Corporation
- Procurement of Two (2) Vacuum Catch Basin Cleaners/ Deeds
Equipment, Inc.
- Procurement of One (1) Ford F350 4x4 Wrecker and One (1) Ford F250
4x4 Ύ Ton Utility Truck/Man-O-War Ford
- Drainage Channel Mowing:
- Black Pond Creek, Lower Mill Creek, Long Run and Selected
Tributaries/Mattingly Brothers, Inc.
- Southern Ditch and Selected Tributaries/Mattingly Brothers Inc.
- FY04 Annual Maintenance Contract Program Contractors: Cherokee
Construction and Excavating, LLC; and TSI Paving
BEARGRASS CREEK WATERSHED AREA TEAM
- Project DRI District 26 Sterling Rd. Drainage
Improvements, Construction Order 1008-087/MTN Construction, Inc.
FLOYDS FORK CREEK WATERSHED AREA TEAM
- Old Henry Rd. Pump Station and Force Main Force Main South
Project, Contract 15,419, Change Orders 1-3/MAC Construction and
Excavating, Inc.
- MFWTP FY04 Construction Contract Program Quarterly
Pre-qualification of Contractors:
- Badgett Constructors, LLC;
- Cherokee Construction and Excavating, LLC;
- Cleaton Parker;
- Delta Electric Co., Inc.;
- Frontier Enterprises, Inc.;
- Hanka Excavating;
- McKinney Painting;
- Pettit Environmental, Inc.;
- Process Control and Instrumentation LLC;
- S & S Panel Fabrication, Inc.;
- T.S.I. Paving
MILL CREEK WATERSHED AREA TEAM
- Project DRI District 12 Arvis-Dellrose Drainage
Improvements, Construction Order 1008-078/United Construction and
Design Group, Inc.
- Project DRI District 12 Chadron Drive Drainage
Improvements, Construction Order 1008-092/S & S Associates
POND CREEK AREA TEAM
- Project DRI District 24 Roberson Run Erosion
Control Project, Construction Order 1008-86/Precision Contracting,
Inc.
- Project DRI District 13 Bridget/Doris Drainage
Improvements, Construction Order 1008-91/MTN Construction, Inc
- Closed Session