September
27, 1999
Mission Statement:
We at MSD build, maintain and operate quality wastewater and stormwater
facilities for the people of the community.
- Call To Order
- Board Meeting Minutes Approval
- Approval of September 13, 1999 MSD Board Meeting
Minutes
- Chair and Executive Director Reports
- Policy Committee Report
- Retainage Policy Repeal
- Procurement Code Amendment
- New Business:
Mill Creek Watershed Area:
- Southwest Ohio River Levee Trail Capital Project,
Phase I and Amendment to the 5-Year Capital
- Valley Station (VS-2C) Collector Project,
Contract 12,550,Change Orders 1-3/K &I
- Valley Trunk (SA-3 & VT-7C) Collector
Project, Contract 12,560,Change Order 1 & 2 Team Contracting
- Valley Trunk (VT-1C) Interceptor Project,
Contract 12,561,Change Order 1 & 2/Reynolds, Inc.
- Devonshire Drive Drainage Improvements, Contract
1002-22/MTN Construction
Beargrass Creek Watershed:
- Lincoln Avenue Drainage Improvements, Contract
12,945/Sang
- Benjamin Lane Drainage Improvements, Construction
Order 1002-23/Basham Construction and Rental
MFWTP Watershed:
- Diversion Structure Modifications, Contract
12,782/Building Crafts
- Main Office Generator Installation, Construction
Order 2000-11/MTN Construction
- Upper Mill Creek Flood Pumping Station Crane Pad,
Construction Order 1999-16/MTN Construction
North County Watershed Area:
- Whipps Mill Road Flood Control Facility,
Contract 12,713,Change Orders 1 & 2/List & Clark Construction
General:
- Annual Maintenance Agreement on SUN Microsystems
Equipment/SUN Microsystems Enterprise Services
- Closed Session
For more information,
please contact: MSD Board |