![]()
|
|
|
||||||||||||||||||||||||||
The DRGWQTC was designed as a 15 million gallon per day preliminary and activated sludge treatment facility. There are no primary sedimentation facilities or sludge processing facilities at the DRGWQTC. Construction is scheduled to begin in April, 1999 to expand the capacity to 19.4 million gallons per day. The raw influent wastewater flows through three coarse bar screens to the influent pump station. Four pumps life the raw wastewater to an aerated grit chamber. From the grit chamber, flow through the remainder of the plant is by gravity. The secondary treatment facilities have the capacity to operate in either a complete mix or contact stabilization activated sludge process. Current operation is with the complete mix mode, utilizing two of the aeration basins. The wastewater flows from the aeration basins to three final settling tanks. Final settling tank effluent flows to chlorine contact basins for disinfection. Following chlorination/dechlorination, final effluent flows to the Ohio River. Settled secondary sludge is wasted to temporary aerobic digesters. The temporary aerobic digesters are the two additional aeration basins that are not currently in service because of low influent organic loading and flow. Waste activated sludge is pumped to the Morris Forman Water Quality Treatment Center (approximately 12 miles) for further processing about once every week. Odor Control
In addition, improvements were made to reduce noise levels from the treatment plant. A noise survey conducted in June 2004 indicated the following:
A public
meeting was held on June 29, 2004 to present the results of the odor and
noise testing. To see the presentation, see "West
County Treatment Plant Noise and Odor Control Project Update"
(806K,
West County Local Limits
More on Water Quality Treatment Centers Area Team Management |
|||||||||||||||||||||||||||
Last
Updated: July 06, 2012
|
|||||||||||||||||||||||||||