Parkwood Channel Improvement Project
| |||
| |||
Project Description
This project involves the construction an estimated 900 linear feet of drainage ditch improvements and stabilization along the rear ditch that runs from 7820 Stephan Drive to 6301 Notto Court. Project will encase two exposed sewer lines that cross the ditch. Project will need to remove several trees growing along the ditch and some fences will need to be removed and replaced. Ditch will not be a concrete bottom but may have concrete in areas to help stabilize. | |||
Need
Eight (8) customer requests will be resolved by the construction of this project, and 15 properties will be affected. | |||
Other Information |