Louisville-Jefferson County

Metropolitan Sewer District

Greenwood Road Combined Assessment
  Customer Service: (502) 587-0603Report as of Wednesday, July 02, 2008
 Budget ID No.A02191
 Project Type:Assessment
 Project Category:Collector
 MSD Project Manager:Paul Meyer
 Jurisdiction:LOUISVILLE
 Metro Council District:12RICK BLACKWELL

 KY Senate District:

37PERRY B. CLARK
 KY House District:44JONI L. JENKINS
Project Schedule
  Project Start:3rd Quarter 2002
  Planning Complete:3rd Quarter 2013
  Easements Complete:2nd Quarter 2003
  Bidding Complete:3rd Quarter 2013
  Construction Complete:1st Quarter 2014
No. Properties:16

Estimated Capital Cost:

      (2008 dollars)

$206,000.00
Service Area:West County WTP
Project Dependent On:Greenwood Roadway (KYDOT)
Project Status:Awaiting Bidding
Area Team:POND CREEK/MILL CREEK
Watershed:MILL CREEK
LOJIC Street Atlas:MAN15
MSD Atlas:BQ206
             Budget ID #  A02191

 

Greenwood Road Combined Assessment

 

 

  Customer Service: (502) 587-0603Report as of Wednesday, July 02, 2008

 

 

Project Description

 

This project will serve 17 properties along Greenwood Road between Rutledge Road and Norwich Boulevard. Each of these properties was originally to be served by the Mill Creek Collectors (MC-11C). However, MSD was unable to construct connections for these properties due to the proposed improvements to Greenwood Road.

 

 

Need

 

The Greenwood Roadway improvement plans are nearing completion and the sanitary sewer plans can now be finalized. Design will be completed in FY03. Construction of the roadway is scheduled for FY05. However, MSD may be allowed to construct the sewers prior to that time.

 

 

Other Information