| | | Budget ID No. | A95013 | | Project Type: | Drainage | | Project Category: | Drainage | | MSD Project Manager: | Carolyn Williams | | Jurisdiction: | LOUISVILLE, SHIVELY | | | Metro Council District: | 12 | | RICK BLACKWELL | | 1 | | JUDY GREEN | KY Senate District: | 33 | | GERALD A. NEAL | | 37 | | PERRY B. CLARK | | KY House District: | 44 | | JONI L. JENKINS | | | |
| | | Project Schedule | | Project Start: | 3rd Quarter 1994 | | Planning Complete: | 3rd Quarter 2013 | | Easements Complete: | 3rd Quarter 2013 | | Bidding Complete: | 3rd Quarter 2013 | | Construction Complete: | 1st Quarter 2015 |
|
| | | No. Properties: | Not Applicable | Estimated Capital Cost: (2008 dollars) | $379,000.00 | | Service Area: | Not Applicable | | Project Dependent On: | Not Applicable | | Project Status: | Awaiting Start |
|
|