Louisville-Jefferson County

Metropolitan Sewer District

Pine Tree/Twin Oaks Roadside Drainage
  Customer Service: (502) 587-0603Report as of Wednesday, July 02, 2008
 Budget ID No.C08051
 Project Type:Drainage
 Project Category:D.R.I.
 MSD Project Manager:Sharlie Khan
 Jurisdiction:LOUISVILLE
 Metro Council District:2BARBARA SHANKLIN

 KY Senate District:

35DENISE HARPER ANGEL
 KY House District:46LARRY CLARK
Project Schedule
  Project Start:2nd Quarter 2009
  Planning Complete:Not Applicable
  Easements Complete:Not Applicable
  Bidding Complete:3rd Quarter 2009
  Construction Complete:4th Quarter 2009
No. Properties:Not Applicable

Estimated Capital Cost:

      (2008 dollars)

$117,000.00
Service Area:Not Applicable
Project Dependent On:Not Applicable
Project Status:Awaiting Start
Area Team:POND CREEK/MILL CREEK
Watershed:POND CREEK
LOJIC Street Atlas:MAN20
MSD Atlas:BM224
             Budget ID #  C08051

 

Pine Tree/Twin Oaks Roadside Drainage

 

 

  Customer Service: (502) 587-0603Report as of Wednesday, July 02, 2008

 

 

Project Description

 

Roadside drainage improvements on sections of Twin Oak, Pine Tree and Otter Ct.

 

 

Need

 

Project needed to alleviate standing water in the driveway and front yards.

 

 

Other Information