  Customer Service: (502) 587-0603Report as of Wednesday, July 02, 2008
 Budget ID No.C08091
 Project Type:Drainage
 Project Category:D.R.I.
 MSD Project Manager:Kerry Lynch
 Jurisdiction:LOUISVILLE
 Metro Council District:25DOUG HAWKINS

 KY Senate District:

38DAN "MALANO" SEUM
 KY House District:28CHARLES MILLER
Project Schedule
  Project Start:2nd Quarter 2009
  Planning Complete:Not Applicable
  Easements Complete:Not Applicable
  Bidding Complete:3rd Quarter 2009
  Construction Complete:1st Quarter 2010
No. Properties:Not Applicable

Estimated Capital Cost:

      (2008 dollars)

$110,000.00
Service Area:Not Applicable
Project Dependent On:Not Applicable
Project Status:Awaiting Start
Area Team:POND CREEK/MILL CREEK
Watershed:POND CREEK
LOJIC Street Atlas:MAO16,MAO16
MSD Atlas:BY210
             Budget ID #  C08091

 

South Dodge Lane Drainage Improvement

 

 

  Customer Service: (502) 587-0603Report as of Wednesday, July 02, 2008

 

 

Project Description

 

Installation of roadside drainage improvements along portions of S Dodge Lane from Youngtown to Linger Ct. Roadside improvements will also be made along Linger Ct.

 

 

Need

 

To help alleviate standing water and customer requests along s Dodge Lane and Linger Ct.

 

 

Other Information