Louisville-Jefferson County

Metropolitan Sewer District

Cadence Court Drainage Improvement Project
  Customer Service: (502) 587-0603Report as of Wednesday, July 02, 2008
 Budget ID No.D02100
 Project Type:Drainage
 Project Category:Drainage
 MSD Project Manager:David Givan
 Jurisdiction:LYNDON
 Metro Council District:17GLEN STUCKEL

 KY Senate District:

36JULIE C. DENTON
 KY House District:32SCOTT BRINKMAN
Project Schedule
  Project Start:Not Applicable
  Planning Complete:Not Applicable
  Easements Complete:Not Applicable
  Bidding Complete:Not Applicable
  Construction Complete:Not Applicable
No. Properties:Not Applicable

Estimated Capital Cost:

      (2008 dollars)

$21,000.00
Service Area:Not Applicable
Project Dependent On:Not Applicable
Project Status:Outside 5 Year Plan
Area Team:FLOYDS FORK/NORTH COUNTY/MFWTP
Watershed:GOOSE CREEK
LOJIC Street Atlas:MAK22
MSD Atlas:AU234
             Budget ID #  D02100

 

Cadence Court Drainage Improvement Project

 

 

  Customer Service: (502) 587-0603Report as of Wednesday, July 02, 2008

 

 

Project Description

 

This construction involves the installation of 200 linear feet of paved ditch at the side of 1406 Cadence Court to connect with the existing 7' flat bottom paved swale.

 

 

Need

 

Construction of this project will help alleviate erosion and maintenance problems along the existing steep ditch at the side of 1406 Cadence Court.

 

 

Other Information

Project scope was planned, but not budgeted before the DRI-1 Program. Work planned beyond the DRI-3 Program.