 Budget ID No.E08243
 Project Type:Drainage
 Project Category:D.R.I.
 MSD Project Manager:John Loechle
 Jurisdiction:WOODLAND HILLS
 Metro Council District:19HAL HEINER

 KY Senate District:

36JULIE C. DENTON
 KY House District:33RON CRIMM
Project Schedule
  Project Start:1st Quarter 2010
  Planning Complete:Not Applicable
  Easements Complete:Not Applicable
  Bidding Complete:2nd Quarter 2010
  Construction Complete:2nd Quarter 2010
No. Properties:Not Applicable

Estimated Capital Cost:

      (2008 dollars)

$19,000.00
Service Area:Not Applicable
Project Dependent On:Not Applicable
Project Status:Awaiting Start
Area Team:FLOYDS FORK/NORTH COUNTY/MFWTP
Watershed:FLOYDS FORK
LOJIC Street Atlas:MAL24,MAL24
MSD Atlas:AY240,BA240
             Budget ID #  E08243

 

Caroldale Lane Drainage Improvement

 

 

  Customer Service: (502) 587-0603Report as of Wednesday, July 02, 2008

 

 

Project Description

 

REGRADE 195 LF OF ROADSIDE SWALE FROM 313 CAROLDALE LN TO 321. REGRADE 5 LF ON SOUTH SIDE OF D/W FOR 313. REGRADE 75 LF OF R/S SWALE FROM D/W AT 307 TO C/B AT 309. REGRADE 40 LF OF R/S SWALE FROM D/W AT 309 CAROLDALE TO C/B. REGRADE 65 LF OF R/S SWALE FROM D/W AT 304 TO C/B. FLUSH D/W CULVERT AT 307 CAROLDALE. REGRADES INCLUDE FROM EDGE OF ASPHALT TO C/L OF SWALE AS NEEDED. SEED, MULCH AND NET DISTURBED AREAS.

 

 

Need

 

Project will relieve road side standing water.

 

 

Other Information