Louisville-Jefferson County

Metropolitan Sewer District

Bailey System DCU3200 Replacement
  Customer Service: (502) 587-0603Report as of Wednesday, July 02, 2008
 Budget ID No.F07080
 Project Type:Treatment Plant
 Project Category:MFWTP
 MSD Project Manager:Jim Emily
 Jurisdiction:LOUISVILLE
 Metro Council District:1JUDY GREEN

 KY Senate District:

33GERALD A. NEAL
 KY House District:42REGINALD MEEKS
Project Schedule
  Project Start:3rd Quarter 2007
  Planning Complete:Not Applicable
  Easements Complete:Not Applicable
  Bidding Complete:4th Quarter 2006
  Construction Complete:3rd Quarter 2008
No. Properties:Not Applicable

Estimated Capital Cost:

      (2008 dollars)

$439,000.00
Service Area:Morris Forman WTP
Project Dependent On:
Project Status:In Progress
Area Team:BEARGRASS CREEK
Watershed:CITY/OHIO RIVER
LOJIC Street Atlas:MAL16,MAL16
MSD Atlas:BA212,BA210
             Budget ID #  F07080

 

Bailey System DCU3200 Replacement

 

 

  Customer Service: (502) 587-0603Report as of Wednesday, July 02, 2008

 

 

Project Description

 

The Bailey Distributed Control Interface System Six consist of seven Distributed Control Units (DCU3200's) throughout the Morris Forman Wastewater Treatment Plant. The DCU3200 is now in the limited phase life cycle where it is not actively sold and parts are limited. The Bailey DCU3200 will be replaced with an Allen-Bradley ControlLogix PLC system using existing Ethernet communication. The Bailey System Six Workstations will be replaced with Intellution Workstations using existing Ethernet communications.

 

 

Need

 

N/A

 

 

Other Information

Changing this system over will be done in house by the MSD Controls group.