Project Schedule
  Project Start:Not Applicable
  Planning Complete:Not Applicable
  Easements Complete:Not Applicable
  Bidding Complete:Not Applicable
  Construction Complete:Not Applicable
No. Properties:Not Applicable

Estimated Capital Cost:

      (2008 dollars)

$11,860,000.00
Service Area:West County WTP
Project Dependent On:Not Applicable
Project Status:Outside 5 Year Plan
Area Team:FLOYDS FORK/NORTH COUNTY/MFWTP
Watershed:MILL CREEK
LOJIC Street Atlas:MAO15,MAO15
MSD Atlas:CA206,CA204
             Budget ID #  F94335

 

WCWTP Liquid Process Phase 3 Project

 

 

  Customer Service: (502) 587-0603Report as of Wednesday, July 02, 2008

 

 

Project Description

 

This project provides for the construction and placement into operation 2 new aeration basins, a solids storage tank and solids transfer pumping station and other ancillary improvements at the West County Wastewater Treatment Plant (WCWTP).

 

 

Need

 

Without expanding the liquid process facilities at the WCWTP, residential, commercial and industrial growth in the WCWTP service area would not be possible.

 

 

Other Information

None.